Business Processes / 3.3.1

No WAN Installation ESME – Prepayment

13 primary steps · 1 associated steps

StepSRVDescriptionComment
18.11Update HAN Device LogChange in InstallCode field attribute – DUIS3.0 onwards
28.13Return Local Command ResponseUpdate SR 8.11 response to DCC
38.13Return Local Command ResponseDevice Alert 0X8F12
3.1Wait For DCC Alert N24/N25If N24 received then go to next step
46.21Request Handover Of DCC Controlled DeviceSupplier Certificate
51.1.1Update Import Tariff (Primary Element)
62.1Update Prepay Configuration
71.6Update Payment ModePayment Mode = ‘Prepayment’
86.8Update Device Configuration (Billing Calendar)
98.13Return Local Command ResponseUpdate SR 6.8 response to DCC
102.3Update Debt
111.5Update Meter Balance‘Adjust’
126.21Request Handover Of DCC Controlled DeviceNetwork Operator Certificate
136.15.1Update Security CredentialsUpdate load controller certs on ESME if APC is present.