Business Processes / 7.4.6
Change Of Supplier Gain – ESME With HCALCS
14 primary steps · 3 associated steps
| Step | SRV | Description | Comment |
|---|---|---|---|
| 1 | 6.23 | Update Security Credential (CoS) | ESME |
| 2 | 6.23 | Update Security Credential (CoS) | HCALCS |
| 2.1 | — | Wait for Alert 0x8F66/0x8F67 | For Future Dated Command |
| 3 | 1.6 | Update Payment Mode | — |
| 4 | 1.1.1 | Update Import Tariff (Primary Element) | — |
| 4.1 | — | Retrieve Change of Mode/Tariff Triggered | — |
| 5 | 4.4.2 | Billing Data Log | Meter Reading |
| 6 | 5.1 | Create Schedule | DSP Schedules |
| 7 | 6.8 | Update Device Configuration (Billing Calendar) | — |
| 8 | 1.5 | Update Meter Balance | — |
| 9 | 3.4 | Update Supplier Name | — |
| 10 | 6.22 | Configure Alert Behaviour | — |
| 11 | — | Update Device Configuration (Auxiliary | — |
| 12 | 6.14.1 | Load Control Description) | N58 alert to DNO |
| 12.1 | — | Update Device Configuration (Auxiliary | — |
| 13 | 6.14.2 | Load Control Scheduler) | N58 alert to DNO |
| 14 | 3.1 | Display Message | — |