Business Processes / 1.7.1
Post Install And Commission Activities โ Network Operator.
6 primary steps ยท 0 associated steps
| Step | SRV | Description | Comment |
|---|---|---|---|
| 1 | 6.24.1 | Retrieve Device Security Credentials (KRP) | Not applicable for Method-2 and Method-3 |
| 2 | 6.15.1 | Update Security Credentials (KRP) | Update Network Operator Certificates. Wait for N42 alert before triggering 6.15.1. The N42 alert will contain the relevant counter values used by the supplier. Since 6.15.1 has anti-replay protection, the Network Operator must use a counter larger than that used by the supplier/. |
| 3 | 6.5 | Update Device Configuration (Voltage) | โ |
| 4 | 6.2.10 | Read Device Configuration (Event And Alert Behaviours) | New R2.0 Service Request |
| 5 | 6.22 | Configure Alert Behaviour | Update ENO Alert Configuration |
| 6 | 5.1 | Create Schedule | Create DSP Schedules for export data |